McNealy Brown were contracted to design, fabricate and install Access For All works spanning four platforms at Virginia Water Station.
The works included:
- Handrails
- CAT Ladders
- Structural Steelwork
- Link Bridges / Lobbies
All fabrications were carried out at our Sittingbourne workshop, followed by a trial setting out of the link bridges and link lobbies. Handrails were finished at our in house powder coating workshop.
The 3 lift shafts were installed during an initial possession. This allowed for other works to be completed by other subcontractors. The remaining installation was postponed but installed in 6no. 3 hour line blocks utilising a 500t crane and a HIAB. The project took ten months from order to completion.