Virginia Water Station

Client
Geoffrey Osbourne Ltd

Main Contractor
Network Rail

Contract Value
£1,100,000

Project Date
2017

Project Datasheet

McNealy Brown were contracted to design, fabricate and install Access For All works spanning four platforms at Virginia Water Station.

The works included:

  • Handrails
  • CAT Ladders
  • Structural Steelwork
  • Link Bridges / Lobbies

All fabrications were carried out at our Sittingbourne workshop, followed by a trial setting out of the link bridges and link lobbies. Handrails were finished at our in house powder coating workshop.

The 3 lift shafts were installed during an initial possession. This allowed for other works to be completed by other subcontractors.  The remaining installation was postponed but installed in 6no. 3 hour line blocks utilising a 500t crane and a HIAB. The project took ten months from order to completion.