There has been great progress thus far with the Dukes Meadow Footbridge as Span 2, Pier 2 & Pier 3 have now been installed at Dukes Meadow!
The 30m long structure made its 36 mile journey up the River Thames early hours Sunday morning from Tilbury Docks.

It successfully arrived at Chiswick on high tide and was installed at 1pm.
The next phase of installation will see Span 1 followed by Span 3 & Pier 4 and then finally Span 4 which will all be installed via a crane.
Well done to everyone working on this project, the footbridge looks fantastic so far.
#DukesMeadowFootbridge #KnightsBrown #Red7Marine #COWI #LondonBoroughofHounslow #MoxonDesign