McNealy Brown took possession of the highway adjacent to Denmark Hill station on 18th December 2020 and assembled the new platform canopy sections (6) for platforms 2/3 & 4 at Denmark Hill. The teams worked around the clock installing the structural steel frame and specialist roof cladding with integrated solar panelling.
During a 52hrs railway closure on Christmas Day/Boxing Day the sections of pre-assembled canopy were lifted into their final position, leaving minimal reworks being necessary to close of the connection in the roof and facia cladding. All works were implemented to programme and the railway was opened as planed on 27th December 2020.
We look forward to similar success on the Phase 2b works, introducing a new Gateline entrance, access ramps and canopies in 2021.