McNealy Brown were provisionally engaged to assist with the design development (ECI). Following design approval McNealy Brown completed the fabrication and installation of the strengthening repair works to the structural members, which date back to 1847.
The strengthening works included:
- Cross Girder Bottom Flange Plates
- Cross Girder Web Plates
- RSA Cranked Angle Stiffeners
- Fabricated Main Girder Stiffeners
- Underslung Beam Strengthening
All of these works were fabricated within our Sittingbourne workshop and delivered to site for installation. The critical strengthening works to spans 7 to 17 were carried out during a 7 day blockade whilst the viaduct was not open to trains. To maximise the 24 hour access, we housed 30 members of our installation team to hotels adjacent to the works. McNealy Brown worked alongside a team of waterjet/shot blasters, followed by specialist painters.
The prominent 1847 Victorian railway structure supports two platforms at Portsmouth and Southsea station. The implemented works will ensure the heritage structure remains in use for many years to come.Â